JLR Slough – October

Progress continues to be in accordance with the programme. In the workshop, the clients workshop contractor has started their first fix of high level equipment and all trades in this building are well advanced to allow the floor tiling to start in early November.

In the main showroom, the ceiling grid is completed and plaster boarding will start 23 October with taping and jointing following to all areas of walls and ceilings.

Both M&E contractors have performed well and continue to be part of a strong team on this site as we look over the next 4 weeks to get areas completed in readiness for the next following trades.