Dick Lovett Jaguar Land Rover

Melksham

  • Our first JLR dealership and successfully completed and handed over on schedule on 1 December 2017.

    We hit the ground running on this negotiated project, and with the benefit of a sustained period of dry weather at the beginning of the project, excavated 600mm off the 4-acre site involving 100 muck away vehicles in and out of the site each day for the period of this operation.

    This progress continued with the erection of the steel frame and the remaining envelope contractors who all performed well.

    Special mention to our M&E and tiling contractors who contributed strongly throughout a well-managed project and enabling us delivering a high-quality finish to the Dick Lovett Group.

  • “The development of our first with JLR and from the outset required us to gain a good understanding of their corporate identity requirements. The team of architects, engineers, contractor and QS all worked closely together to iron out as many issues as possible before we started on site.

    Our own requirements then changed in terms of finish date: bringing it forward many weeks. SquareOne responded very well to adjust the programme to fit our requirements. We were blessed with a very long dry spell at the beginning of the contract, and SquareOne were able to benefit from these good conditions.

    Very pleasingly the finished building was handed over on time and in budget. We are now very proud to operate our new Jaguar Land Rover business from much admired premises.

    Many thanks to the whole SquareOne team.

    Peter Lovett – Chairman – Dick Lovett